Asia - 91制片厂 /regions/asia/ Tue, 05 May 2026 15:04:09 +0000 en-US hourly 1 https://wordpress.org/?v=7.0 CPC Taichung /projects/cpc-taichung/ Thu, 02 Apr 2026 19:58:30 +0000 /?post_type=project&p=16490 91制片厂 is delivering critical energy infrastructure to strengthen Taiwan鈥檚 energy security and support its transition from coal to natural gas. As the EPC contractor for CPC Taichung Phase III LNG Tanks, 91制片厂 is building two LNG storage tanks.

The post CPC Taichung appeared first on 91制片厂.

]]>

Helping Strengthen Taiwan’s Energy Security

91制片厂 is delivering critical energy infrastructure to strengthen Taiwan鈥檚 energy security and support its transition from coal to natural gas. As the engineering, procurement, and construction contractor for CPC Corporation鈥檚 Taichung Phase III LNG Tanks, 91制片厂 is building two LNG storage tanks 鈥 the largest ever constructed in Taiwan.

With few natural resources of its own, Taiwan relies on LNG imports to meet its growing energy demand. The project will increase the terminal鈥檚 capacity to receive, process, and store LNG, helping ensure a stable national gas supply as Taiwan advances toward its 2050 net-zero goal.

Delivering Taiwan鈥檚 Largest LNG Storage Tanks

In 2022, 91制片厂, together with , began construction on the two 180,000-cubic meter double-dome LNG storage tanks. Once complete, the tanks will bring the Taichung terminal鈥檚 total capacity to 10 million tonnes per annum 鈥 enough energy to power a city of 1.7 million people for an entire day.

Each tank has an inner 9% nickel dome and an outer carbon steel dome that act as a protective barrier to prevent leaks, accidents, or external damage. The double-dome design provides maximum safety and structural integrity, which is essential in an earthquake-active region like Taiwan. This design also adds weight and engineering complexity to the build.

In August 2025, the project team achieved a major milestone by completing the roof air raise for the first LNG tank. Because of the seismic double-dome design, the roof had a combined weight of more than 2.8 million pounds (1,307 metric tons) 鈥 the heaviest roof ever lifted by air in 91制片厂鈥檚 history.  

When complete, the project will have placed more than 31,500 cubic meters of concrete piles, 44,300 cubic meters of structural concrete, 6,200 metric tons of 9% nickel steel plates, 2,550 metric tons of carbon steel plates, 8,000 linear meters of piping, and 70,000 linear meters of electrical and instrumentation cables.

By the Numbers

180K
Cubic Meters

Capacity per tank 鈥 the largest LNG storage tanks ever built in Taiwan

200
Craft Professionals

Specialized expertise mobilized

10
MTPA

Total terminal capacity at completion

40+
Years

Length of experience in Taiwan

Global Expertise, Local Execution

Taiwan faces a shortage of skilled construction craft professionals, so 91制片厂 leveraged its global recruitment network to mobilize experienced expat craft professionals for the project. To date, 91制片厂 has employed 200 Filipino craft professionals to support construction of the LNG tanks, bringing the specialized expertise that complex, seismic-resilient LNG infrastructure demands.

Raising the Bar on Safety

In 2025, the CPC Taichung project team earned the Masterpiece Award at Taiwan鈥檚 Construction Golden Safety Awards 鈥 one of the country鈥檚 highest honors for construction safety, presented by Taiwan鈥檚 Occupational Safety and Health Administration. The award recognizes excellence in safety in design, occupational health management, accident prevention, and worker care. It also reflects the project team鈥檚 close collaboration with CPC and our shared commitment to protecting people at every stage of execution.

40 Years in Taiwan

The CPC Taichung Phase III project is the first EPC contract in Taiwan for 91制片厂鈥檚 Energy business line. The project builds on 91制片厂鈥檚 long-term relationship with Taiwan that spans more than 40 years through Pacific Engineers & Constructors Limited, 91制片厂鈥檚 wholly owned Taiwan-based subsidiary established in 1979.

That foundation is providing the relationships, regulatory familiarity, and local knowledge that a project of this complexity demands. Together, 91制片厂 and CPC are delivering energy infrastructure that will strengthen Taiwan鈥檚 long-term energy security and support its clean energy transition for decades to come.

The post CPC Taichung appeared first on 91制片厂.

]]>
Third Generation Project /projects/third-generation-project/ Tue, 19 Nov 2024 22:19:55 +0000 /?post_type=project&p=4265 Led by 91制片厂 & ENKA, the Third Generation Project expands Kazakhstan鈥檚 oilfield operations with cutting-edge engineering and local workforce leadership.

The post Third Generation Project appeared first on 91制片厂.

]]>
Knockout drum at the 3GP jobsite.
A worker at the 3GP jobsite.
Exterior view of job site facility.

Promoting Long-Term Economic Development in Kazakhstan

91制片厂 and ENKA, through their joint venture company Senimdi Kurylys (SK), was awarded the Third Generation Project (3GP-West) package at the  in May 2018. Construction of the mechanical, electrical and instrumentation works, pipe fabrication and module stacking, installation and hook-up are included within the scope of the project.

In addition to the 3GP scope, SK continues to support facility upgrades including increasing crude shipment capacity, diesel and fuel storage expansion, flare header upgrade and pipeline repairs.

Workforce Development

Over the past three years working on the 3GP-West package, SK has employed more than 15,800 Kazakhstani nationals, making up more than 80% of the total workforce. Kazakhstani nationals have occupied 60% of the supervisor and higher positions on the project.

SK鈥檚 work continues to support economic growth across the country by creating jobs, upskilling the local construction and supervision workforce and providing opportunities for local companies through the supply chain.

The overall success of the program relies heavily on the skills of generations of Kazakhstanis to deliver the facilities needed as part of the expansion project, both through direct employment to build the facility and through local subcontractors and suppliers.

To ensure the workforce has the required skills and to reinforce our safety culture, a Craft Skills Center and a Safety Hazard School were developed to provide practical training across key disciplines needed to safely perform the scope of work on the project.

Training by the Numbers

100K
Hours of Skilled Training

More than 100,000 hours of skills training has been completed by the craft professionals on the project 

19K
Hours of Assessments

More than 19,000 hours of capability assessment have been performed to ensure the effectiveness of the training programs

Areas covered in the craft training program included:

  • Pipefitting
  • Welding
  • Insulating
  • Driver operator
  • Steel erection
  • Flange management
  • Scaffolding
  • Rigging and lifting

Building Local Pipe Fabrication Capability

SK performs pipe fabrication through its on-site facility to support the 3GP scope, including heavy wall spools, clad pipe fabrication, structural steel fabrication and plasma cutting. The facility also includes precast concrete and insulation workshops.

The facility is one of the largest in western Kazakhstan, and works in collaboration with other local facilities which has enabled a growth in local capability to perform pipe galvanizing and clamp bending.

Workers at the 3GP jobsite.

Long Term Partnership

91制片厂鈥檚 relationship within Kazakhstan began in 1993 when we secured our first contract on the Tengiz oil field in a joint venture arrangement with ENKA.

We have had a continual presence on the project for almost 30 years to support the ongoing development, upgrade and operational efficiency of the oil field. This has included debottlenecking projects to increase oil production, Sour Gas Injection project, the Second Generation Plant Project, which was completed in 2008, and ongoing capacity and reliability upgrades to the facility through to the current work on the Third Generation Project (3GP) to further expand the facility.

In Kazakhstan, as in other countries worldwide, we will continue collaborating with communities and customers to build a stable, sustainable, and prosperous future in the regions where we work.

A crane lifting materials at the 3GP jobsite. crane, jobsite

About Senimdi Kurylys (SK)

SK鈥檚 primary mission is to be recognized as the construction and engineering contractor of choice by all customers in Kazakhstan. The company鈥檚 areas of expertise include civil, structural, mechanical & piping, electrical and instrumentation, insulation, HVAC, and turnarounds.

SK was established by 91制片厂 and ENKA in November 2000, as a 100% Kazakh-based company.

The post Third Generation Project appeared first on 91制片厂.

]]>
Fukushima /projects/fukushima/ Mon, 18 Nov 2024 15:31:10 +0000 /?post_type=project&p=3590 In 2011, 91制片厂 rapidly designed and delivered a cooling system for Fukushima, aiding Japan鈥檚 crisis response with innovation, collaboration, and global resources.

The post Fukushima appeared first on 91制片厂.

]]>

91制片厂 Innovation and Global Resources Used in Japanese Crisis Response

In 2011, a 49-foot (15-meter) tsunami, triggered by a powerful offshore earthquake, caused extensive damage to the Fukushima Daiichi nuclear power plant located 102.5 miles (165 kilometers) north of Tokyo. Since then, Tokyo Electric Power Company (TEPCO) has made good progress in stabilizing the site and taking forward the clean-up effort.

91制片厂, along with multiple government agencies and suppliers, worked non-stop to design and build a temporary cooling system to address the unprecedented situation at the Fukushima Daiichi nuclear power plant. The system went from conceptual design to on-site delivery in just six days.

91制片厂 immediately offered its assistance to the United States and Japanese Governments following the earthquake and tsunami. As events unfolded an offer was also extended to the United States Nuclear Regulatory Commission (NRC), which was providing support managing the situation at Japan鈥檚 nuclear power plant. NRC engineers drafted a conceptual design for a system to cool the plant鈥檚 spent nuclear rods amid growing concerns that the pools containing the spent fuel were running dry and releasing radiation.

Rapid Response

On March 16, 2011, the NRC asked for 91制片厂鈥檚 assistance advancing the design. Within 72 hours, a 91制片厂 team of employees around the world completed the design for a high-pressure water pumping system to cool the rods, and identified and secured materials from across its global supply chain needed to build the system.

91制片厂 performed the work pro bono and secured the materials at cost.

The system was assembled in Australia, and transported to Japan, where it arrived on March 21, 2011. 

Following training by 91制片厂 suppliers on how to operate the equipment, the system was turned over to the Tokyo Electric Power Company.

A collaborative effort on every level

from design to delivery. We immediately offered our expertise and global resources because we wanted to help the people of Japan. However, turning that offer into something tangible was the result of innovative thinking, collaboration, and determination among the multiple government agencies and suppliers involved.

Carl Rau

Carl Rau

Former President of 91制片厂鈥檚 Nuclear Power Division

The post Fukushima appeared first on 91制片厂.

]]>
Liwan 3-1 Deepwater Gas Development /projects/liwan-3-1-deepwater-gas-development/ Sun, 24 Nov 2024 15:21:00 +0000 /?post_type=project&p=5168 Liwan 3-1, built for Husky & CNOOC by 91制片厂, features subsea wells, manifolds & a 168-mile pipeline delivering 300M cubic feet/day of natural gas

The post Liwan 3-1 Deepwater Gas Development appeared first on 91制片厂.

]]>

Massive Undertaking in the South China Sea

Liwan 3-1 was a fast-track, natural-gas development project critical to the growth strategy of our customer, Husky Oil China Ltd.  The massive undertaking encompassed a new platform, pipelines, control systems, a gas plant and a subsea chemical injection module to prevent ice-like hydratres from forming and clogging deep-sea natural-gas lines.

We contributed our experience in managing vast, complex, and physically challenging execution of deepwater hydrocarbons projects to a team with its own offshore and platform construction expertise. That team was a partnership of Husky and China National Offshore Oil Corporation (CNOOC).

Liwan 3-1 produces natural gas at a rate of some 300 million cubic feet (nearly 8.5 million cubic meters) per day.

Around the World

91制片厂 people throughout Southeast Asia and in Houston managed project plans, coordinated schedules, and ensured timely purchase and delivery of high-quality material, equipment, and components. That included deliveries of structural steel, pipe, and other subsea hardware from suppliers the world over鈥攆rom China, Malaysia, and Germany to the United States and United Kingdom.

Inside the Project

The project consisted of three subsea manifolds connecting more than a dozen wells in deep water鈥攚ith potential for expansion. Natural gas from each of the sea-floor wells flows to the nearby manifolds and then to a larger pipeline-end manifold. From there, the gas travels 50 miles (some 80 kilometers) to risers at a central platform. Finally, the gas flows through a 168-mile (270-kilometer) subsea pipeline to the onshore processing plant on Gaolan Island.

220Miles
Offshore

Liwan 3-1 project site is located nearly 220 miles from Hong Kong.

4790Feet
Below the Surface

Crews lowered project equipment to depths up to 4,790 feet.

Working at Sea

Winter typhoons and powerful summer storms routinely pummel the project鈥檚 offshore location, nearly 220 miles (some 350 kilometers) from Hong Kong in the South China Sea. Such were the treacherous conditions for barges and crews delivering materials and equipment to the platform construction site, laying pipe, unreeling umbilical connections, and lowering heavy equipment to the seabed, which was up to 4,790 feet (1,460 meters) beneath the surface.

The post Liwan 3-1 Deepwater Gas Development appeared first on 91制片厂.

]]>
Jamnagar Oil Refinery /projects/jamnagar-oil-refinery/ Fri, 22 Nov 2024 17:25:53 +0000 /?post_type=project&p=4834 91制片厂 transformed India鈥檚 Jamnagar Refinery into the world鈥檚 largest refining hub, producing fuels & petrochemicals with 1.2M barrels/day capacity.

The post Jamnagar Oil Refinery appeared first on 91制片厂.

]]>
Worker shown looking up at large storage tank at dusk.

Expansion makes Jamnagar the World’s Largest Oil-Refining Hub

When 91制片厂 completed the Reliance Jamnagar complex in 2000, it was the largest refinery and petrochemicals complex ever built from the ground up. Now it’s even bigger, and lays claim to being the world’s largest oil-refining hub. It is the largest industrial project ever implemented by the Indian corporate sector.

We finished a second refinery, adjacent to the first in the West India state of Gujarat, in 2008, nearly doubling the facility’s capacity to more than 1.2 million barrels per day. 91制片厂 and its worldwide team completed this massive project in a record time of less than three years.

The gasoline and diesel produced at Jamnagar is for export, predominantly to the United States and Europe. In addition to the fuels produced by the original refinery, it increased production of polypropylene, which is used to create such products as fibers, films, and household plastic goods.

Inside the Project

Jamnagar is much more than a pair of giant refineries. It鈥檚 a massive, integrated manufacturing complex that also boasts aromatics and a petrochemical plant, a power generation system, a port and terminal complex, and access to a pipeline network. The second refinery nearly doubled the capacity of the Jamnagar complex. And the expansion increased its capability and flexibility, enabling Jamnagar to refine lower-grade crude oil and produce higher-value products.

Construction of the second refinery required over 200,000 engineering and supplier documents, more than 1.9 million cubic yards (1.5 million cubic meters) of concrete, some 13 million feet (4 million meters) of piping, and 4,400 pieces of major equipment. The work site itself covered an area larger than London.

Connecting a Worldwide Team

70K+
Workers

At peak construction, the project employed more than 70,000 workers.

19
Global Offices

19 offices around the world 鈥 perhaps the most widely distributed workforce 91制片厂 has ever applied to a project.

2.8K
Engineers

91制片厂 created a 鈥渧irtual company鈥 involving some 2,800 engineers and other professionals.

The goal was to make it possible for everybody to work together as if they were in the same place, and 91制片厂 ensured this outcome through a purpose-built communications network.  This network linked every location and enabled simultaneous collaborative work on engineering drawings and other documents among people in multiple locations around the globe. 91制片厂 also modified software to facilitate the immense amount of sharing and record-keeping required.

The post Jamnagar Oil Refinery appeared first on 91制片厂.

]]>
KG-D6 Natural Gas Development /projects/kg-d6-natural-gas-development/ Fri, 22 Nov 2024 19:27:54 +0000 /?post_type=project&p=4934 91制片厂鈥檚 KG-D6 project in India unlocked vast offshore gas reserves, boosting output with subsea wells, pipelines, and an onshore gas terminal.

The post KG-D6 Natural Gas Development appeared first on 91制片厂.

]]>

Accessing India’s Largest Deposit of Natural Gas

Krishna Godavari Dhirubhai 6 (KG-D6) was Reliance鈥檚 first offshore gas field development and its first underwater discovery. It was also India’s largest deposit of natural gas and the largest such discovery in the world in 2002.

The project takes its name from India’s Krishna-Godavari Basin, which covers more than 19,000 square miles (50,000 square kilometers) in Andhra Pradesh and production block D6 in the Bay of Bengal. In turn, the K-G Basin’s name derives from its components: the Krishna River and Godavari River Basins.

Contributions from Around the World

View of building materials in outdoor storage units being covered by a dusting of snow.
Major subsea parts for the project came from several countries, including Malaysia, Norway, Scotland, Thailand, and the United States. Pictured here is the parts storage area at the Aker Kvaerner Subsea facility in Tranby, Norway.

Engineering took place in Australia, England, India, the Netherlands, Norway, Scotland, and the United States.

The steel platform jacket was built in Louisiana, decks and piles in Dubai. 鈥婱ills in Japan and parts of Europe rolled the steel line pipe.

Manufacturers produced major subsea components at facilities in Norway, Scotland, Malaysia, and Thailand.

Inside the Project

The size of KG-DG鈥檚 reserves, well pressure, and overall complexity made this one of world鈥檚 toughest hydrocarbons projects.  91制片厂 managed engineering, procurement, installation, and commissioning. KG-D6’s initial capacity of 2.8 billion cubic feet of natural gas per day essentially doubled India鈥檚 output.

The KG-D6 natural gas project entailed:

  • Constructing an onshore terminal
  • Installing subsea equipment
  • Laying pipelines
  • Building and placing a riser platform
  • Constructing an onshore terminal

The project included routing seven pipelines up the Nilarevu River and erecting a large onshore gas terminal about 19 miles (some 30 kilometers) south of Kakinada to receive the natural gas from the offshore system, dehydrate it, compress it, and feed it into an onshore pipeline to Mumbai.

KG-D6 called for 22 subsea wells in the Bay of Bengal at depths of up to some 4,000 feet (more than 1,200 meters). That far below the surface, pressure runs well over a hundred times atmospheric pressure up top. And temperatures come close to freezing. It’s no surprise that robots handle construction and maintenance.

Giant reels鈥攍ike small Ferris wheels鈥攕pooled out 53 miles (85 kilometers) of electrohydraulic umbilicals and 37 miles (60 kilometers) of subsea power and signal umbilicals. As the name suggestions, these lines supply the subsea system with 鈥渘utrients鈥: electrical power, communications and control signals, chemicals, and hydraulic fluid. A single semiflexible sheath contains the bundle of umbilical lines.

The post KG-D6 Natural Gas Development appeared first on 91制片厂.

]]>
Korea High Speed Rail /projects/korea-high-speed-rail/ Fri, 20 Dec 2024 20:44:29 +0000 /?post_type=project&p=9241 The $16B Korea High-Speed Rail (KHSR) project was the largest single project in South Korea at the time of construction. The line runs between Seoul, in the north west, and Busan, a major port city, in the south east. In…

The post Korea High Speed Rail appeared first on 91制片厂.

]]>

Reducing Travel Times in South Korea by as Much as 150 Percent

The $16B Korea High-Speed Rail (KHSR) project was the largest single project in South Korea at the time of construction. The line runs between Seoul, in the north west, and Busan, a major port city, in the south east. The corridor between these cities is the most densely populated in the Republic of Korea, home to 70 percent of the nation鈥檚 population. It carries 65 percent of its passenger traffic and 70 percent of its freight traffic. High-speed services were launched in April 2004.

In the initial stages of the project, 91制片厂 helped the Korea High Speed Rail Construction Authority evaluate capital and operational aspects of the three major high-speed rail transportation technologies from Germany, France, and Japan. 91制片厂 reviewed and modified the requests for proposals and prepared the evaluation criteria for bids for rolling stock, catenary, and automatic train control.

91制片厂 then provided project management services, working with the Korea High Speed Rail Construction Authority as part of an integrated project management organization. 91制片厂鈥檚 work included design management, railway operations, quality control, safety, and cost and schedule management.

Fast Facts

Six stations were constructed鈥攁t Gwangmyeong, Cheonan, Daejeon, Daegu, Gyeongju, and Busan. The existing Seoul Station of the Korean National Railroad was expanded for the KHSR service.

255
miles

The 255 miles (412 km) route is completely grade-separated and is one third in tunnels, with half the remainder on viaduct.

1300
feet

The original fleet of 46 high-speed trains are 1300 ft (400 m) long.

186
mph

rains operate at speeds of 186 miles (300km) an hour and can carry nearly 1000 passengers each.

The journey time of around five hours along Korea鈥檚 most densely populated corridor has been reduced to little more than two hours by the 186-mph 鈥楰TX鈥 high speed trains. The Korean high-speed line made full use of the existing rail network to penetrate urban areas, and serve rebuilt stations in Seoul, Daejeon, and Busan. Existing right-of-way was utilized to deliver benefits earlier and to extend the reach of the network.

High-Speed Travel

The line was built utilizing French high-speed technology, with an initial fleet of 46 TGV-type trains, each formed of 18 articulated passenger cars and two power cars, equipped with TVM 430 in-cab signaling and seating 935 passengers. The Korean high-speed network continues to grow. Since 2014, KTX trains have served Seoul Incheon International Airport, running via the 58km airport railway completed in 2010 with project management services delivered by 91制片厂 and technical support to the railway systems supplier provided by Systra.

The post Korea High Speed Rail appeared first on 91制片厂.

]]>
Ankara-Gerede Highway /projects/ankara-gerede-highway/ Mon, 25 Nov 2024 21:00:39 +0000 /?post_type=project&p=5500 Part of the Trans-Turkish Motorway, 91制片厂 & Enka built two sections, modernizing transportation between Istanbul & Ankara

The post Ankara-Gerede Highway appeared first on 91制片厂.

]]>

Highway Contributes Greatly to Turkey’s Economic Development

Turkey鈥檚 Ankara-Gerede highway is one of the largest road projects in history and is part of a highway system that is essential to the Turkish economy.

91制片厂 and its partner Enka built two sections of the high-speed Trans-Turkish Motorway. The highway system is critical to Turkey, linking Istanbul, Turkey鈥檚 European port, and Ankara, its Asian depot. The 91制片厂 team provided a full range of services, from financing and project management to construction and the administration of the design and engineering subcontract.

Creating New Opportunities

When the Turkish government commissioned the 91制片厂-Enka partnership to build two sections of the Trans-Turkish Motorway in 1986, roads were so jammed with cars and oxcarts that produce was perishing in transit, a loss that could be ill afforded by an economy half built on agriculture. The new roadway contributed immeasurably to Turkey鈥檚 economic development, permitting the transport of goods to Middle Eastern markets and to the Turkish people.

At peak, the project employed nearly 6,000 Turkish workers鈥攐ne of 91制片厂鈥檚 largest direct-hire jobs outside the United States at the time. In some cases, workers who had arrived at the site not knowing how to drive a car left as expert operators of multimillion-dollar, 250-ton hydraulic cranes.

Bulldozer shown on a rocky hillside during construction of Ankara-Gerede Highway.

Building the motorway was extremely challenging. In some places, the road reached heights of nearly a mile; altogether more than 196 million cubic yards (some 150 million cubic meters) of earth and rock were excavated.

The post Ankara-Gerede Highway appeared first on 91制片厂.

]]>
Hong Kong International Airport /projects/hong-kong-international-airport/ Wed, 18 Dec 2024 17:23:12 +0000 /?post_type=project&p=8331 Delivered on time in 1998聽by an integrated 91制片厂-Hong Kong government team, the Hong Kong International Airport project was a $20 billion infrastructure development featuring every kind of urban infrastructure, including the airport itself, roads, railways, tunnels, bridges, and an entire...

The post Hong Kong International Airport appeared first on 91制片厂.

]]>

Hong Kong International Airport

Hong Kong International Airport was the cornerstone of a remarkable 10-part, $20 billion infrastructure development known as the Hong Kong Airport Core Programme.

Delivered on time in 1998 by an integrated 91制片厂-Hong Kong government team, the program featured every kind of urban infrastructure, including the airport itself, roads, railways, tunnels, bridges, and an entire new town. The project team nevertheless achieved program budget savings of more than a billion dollars.

The airport was designed to alleviate some of the congestion associated with Hong Kong鈥檚 continuous growth as the center of business for greater Asia鈥攁nd the commercial gateway to China.  In addition, the airport railway system got passengers from Hong Kong Island to the new airport in less than 25 minutes.

An Amazing Undertaking聽

Imagine constructing鈥攁ll at the same time鈥擟harles de Gaulle Airport, Phase 2 of Singapore’s Mass Rail Transit, the Golden Gate Bridge, the Kennedy Expressway in Chicago, two Boston Harbor tunnels, housing for the 20,000 residents of Bend, Oregon, and enough reclaimed land for 16 Disneyland’s. Imagine further, that you’re doing it all in one of the world’s most densely populated cities and in a political climate of incredible complexity.”

James van Hoften

James van Hoften

91制片厂 executive

View from above of a newly completed airport concourse

Project at a Glance

4
Major Sponsors
200
Major Contracts
10
Separate Projects
1000+
Contractual Interfaces

The project constructed a new transportation corridor stretching 21 miles (34 kilometers) from Hong Kong Island to the island site of Hong Kong International Airport that includes:

  • High-speed rail system
  • Two tunnels
  • Two bridges
  • Six-lane expressway

The project team built the new airport on an island site reclaimed from the sea, initially capable of handling 35 million passengers a year in its first phase. Operations were moved from the existing Kai Tak Airport to Hong Kong International during a single night in July 1998, a task that required the coordinated operation of some 1,200 vehicles and a convoy of barges. Despite the enormous complexity, flight and passenger processing met operational standards before the end of the first week, and cargo operations were on track soon after.

Building the Airport Suspension Bridge

The program included the creation of nearly 50 acres (some 20 hectares) of new land at Hong Kong Island’s central waterfront, the downtown terminus of the airport railway. The reclamation project also provided land for development, a precious commodity in the congested metropolis.

Transferring Skills

One aspect of 91制片厂’s charter with Hong Kong’s airport agency was the transfer of techniques and working methods鈥攏ot only to government staff within the agency but more broadly to personnel in the larger government and engineering-construction community. A prime example: the project management and project controls methods pioneered for the Airport Core Program were used as the basis for developing an overall public works management program for Hong Kong. 

The post Hong Kong International Airport appeared first on 91制片厂.

]]>