Energy | 91ÖÆÆ¬³§ /markets/energy/ Tue, 09 Jun 2026 14:41:25 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 CPC Taichung /projects/cpc-taichung/ Thu, 02 Apr 2026 19:58:30 +0000 /?post_type=project&p=16490 91ÖÆÆ¬³§ is delivering critical energy infrastructure to strengthen Taiwan’s energy security and support its transition from coal to natural gas. As the EPC contractor for CPC Taichung Phase III LNG Tanks, 91ÖÆÆ¬³§ is building two LNG storage tanks.

The post CPC Taichung appeared first on 91ÖÆÆ¬³§.

]]>

Helping Strengthen Taiwan’s Energy Security

91ÖÆÆ¬³§ is delivering critical energy infrastructure to strengthen Taiwan’s energy security and support its transition from coal to natural gas. As the engineering, procurement, and construction contractor for CPC Corporation’s Taichung Phase III LNG Tanks, 91ÖÆÆ¬³§ is building two LNG storage tanks — the largest ever constructed in Taiwan.

With few natural resources of its own, Taiwan relies on LNG imports to meet its growing energy demand. The project will increase the terminal’s capacity to receive, process, and store LNG, helping ensure a stable national gas supply as Taiwan advances toward its 2050 net-zero goal.

Delivering Taiwan’s Largest LNG Storage Tanks

In 2022, 91ÖÆÆ¬³§, together with , began construction on the two 180,000-cubic meter double-dome LNG storage tanks. Once complete, the tanks will bring the Taichung terminal’s total capacity to 10 million tonnes per annum — enough energy to power a city of 1.7 million people for an entire day.

Each tank has an inner 9% nickel dome and an outer carbon steel dome that act as a protective barrier to prevent leaks, accidents, or external damage. The double-dome design provides maximum safety and structural integrity, which is essential in an earthquake-active region like Taiwan. This design also adds weight and engineering complexity to the build.

In August 2025, the project team achieved a major milestone by completing the roof air raise for the first LNG tank. Because of the seismic double-dome design, the roof had a combined weight of more than 2.8 million pounds (1,307 metric tons) — the heaviest roof ever lifted by air in 91ÖÆÆ¬³§â€™s history.  

When complete, the project will have placed more than 31,500 cubic meters of concrete piles, 44,300 cubic meters of structural concrete, 6,200 metric tons of 9% nickel steel plates, 2,550 metric tons of carbon steel plates, 8,000 linear meters of piping, and 70,000 linear meters of electrical and instrumentation cables.

By the Numbers

180K
Cubic Meters

Capacity per tank — the largest LNG storage tanks ever built in Taiwan

200
Craft Professionals

Specialized expertise mobilized

10
MTPA

Total terminal capacity at completion

40+
Years

Length of experience in Taiwan

Global Expertise, Local Execution

Taiwan faces a shortage of skilled construction craft professionals, so 91ÖÆÆ¬³§ leveraged its global recruitment network to mobilize experienced expat craft professionals for the project. To date, 91ÖÆÆ¬³§ has employed 200 Filipino craft professionals to support construction of the LNG tanks, bringing the specialized expertise that complex, seismic-resilient LNG infrastructure demands.

Raising the Bar on Safety

In 2025, the CPC Taichung project team earned the Masterpiece Award at Taiwan’s Construction Golden Safety Awards — one of the country’s highest honors for construction safety, presented by Taiwan’s Occupational Safety and Health Administration. The award recognizes excellence in safety in design, occupational health management, accident prevention, and worker care. It also reflects the project team’s close collaboration with CPC and our shared commitment to protecting people at every stage of execution.

40 Years in Taiwan

The CPC Taichung Phase III project is the first EPC contract in Taiwan for 91ÖÆÆ¬³§â€™s Energy business line. The project builds on 91ÖÆÆ¬³§â€™s long-term relationship with Taiwan that spans more than 40 years through Pacific Engineers & Constructors Limited, 91ÖÆÆ¬³§â€™s wholly owned Taiwan-based subsidiary established in 1979.

That foundation is providing the relationships, regulatory familiarity, and local knowledge that a project of this complexity demands. Together, 91ÖÆÆ¬³§ and CPC are delivering energy infrastructure that will strengthen Taiwan’s long-term energy security and support its clean energy transition for decades to come.

The post CPC Taichung appeared first on 91ÖÆÆ¬³§.

]]>
Velocys /projects/velocys/ Wed, 13 May 2026 19:28:48 +0000 /?post_type=project&p=15737 Aviation is one of the hardest to decarbonize sectors, which is why sustainable fuels technology company Velocys made it its mission to produce sustainable aviation fuel (SAF). 91ÖÆÆ¬³§ has worked with Velocys on a number of projects.

The post Velocys appeared first on 91ÖÆÆ¬³§.

]]>

Advancing Sustainable Aviation Fuel in the UK

Aviation is one of the hardest sectors to decarbonize — and one of the most urgent. 91ÖÆÆ¬³§ is helping to change that. Through a long-term partnership with Velocys, a pioneer in sustainable fuels technology, we’ve provided front-end engineering and design services for two landmark projects in the UK that are laying the technical and industrial groundwork for large-scale sustainable aviation fuel (SAF) production.

SAF is a cleaner alternative to conventional jet fuel — one that can reduce CO2 emissions throughout its lifecycle by up to 80% and be used in existing aircraft without modification. Our work with Velocys also supports the UK’s ambitious carbon emissions goals, including reaching net zero by 2050 and zero domestic aviation emissions by 2040. The proposed Altalto Immingham plant and e-Alto project are part of how that ambition gets turned into reality — introducing sustainable fuel options for global markets and accelerating the energy transition.

By the Numbers

Up to 80%
Lower Emissions

Up to 80% lower lifecycle CO2 emissions with SAF compared with traditional jet fuels

70K
Tonnes

70,000 tonnes of CO2 avoided annually with the e-Alto process

350K
Tonnes

350,000 tonnes of CO2 avoided annually with the proposed Altalto facility

1000
Flights

1,000 flights from London to New York per year could be powered by Altalto’s expected output

Altalto: Turning Waste Into Fuel

Velocys selected 91ÖÆÆ¬³§ to lead the front-end engineering and design (FEED) study for the proposed Altalto Immingham plant, one of the most advanced waste-to-SAF projects in the world. The project is a joint development between Velocys and British Airways, supported by a £27 million grant from the U.K. Department for Transport’s Advanced Fuels Fund.

The plant was designed to convert residual household and commercial waste — material that would otherwise go to the landfill — into jet fuel using Velocys’ Fischer-Tropsch technology.

At full capacity, the plant was engineered to produce approximately 20 million gallons (80 million liters) of SAF per year, with net negative carbon emissions. That’s enough SAF to power 1,000 flights from London to New York annually, saving 350,000 tonnes of carbon dioxide each year and reducing greenhouse gas emissions by 150% compared to conventional jet fuel.

e-Alto: The Next Generation of Jet Fuel

91ÖÆÆ¬³§ also conducted the pre-FEED for e-Alto, a next-generation e-fuels project that takes a different approach to SAF production. Unlike Altalto, this method is powered entirely by renewable electricity rather than waste.

The process combines green hydrogen, produced by electrolysis using renewable power, with carbon dioxide captured from a local waste-to-energy power station through a reverse water-gas shift process to make syngas — a mixture of hydrogen and carbon monoxide. The syngas is then converted into liquid fuels using Velocys’ proprietary Fischer-Tropsch gas-to-liquid technology. The result is a low-carbon SAF made from captured emissions and clean electricity, with no new carbon introduced into the process.

91ÖÆÆ¬³§â€™s pre-FEED assessed the feasibility and technical requirements to make SAF at the plant, including producing an early-stage cost estimate. This critical work determines if the technology is viable at scale.

At full capacity, e-Alto has the potential to produce approximately 500 barrels of SAF per day — helping avoid nearly 70,000 tonnes of carbon dioxide emissions annually. 

A Partnership Built on Trust

Our work with Velocys is anchored by a master relationship agreement and a continuing technical services agreement (CTSA) — establishing a framework for ongoing collaboration as we develop an engineering, procurement, and construction execution model for the sustainable fuels projects.

Our Technologies & Solutions team was instrumental in launching this partnership, conducting a due diligence review of Velocys’ chosen process technologies — including municipal solid waste processing, gasification, and the Fischer-Tropsch gas-to-liquids process — and laying the technical groundwork.

In January 2026, 91ÖÆÆ¬³§ signed a three-year extension to the CTSA, a testament to the trust and momentum built through years of collaboration. Altalto and e-Alto are two of three SAF projects 91ÖÆÆ¬³§ has undertaken with Velocys, alongside the Bayou Fuels Project in the United States. These projects don’t just demonstrate what’s possible — they help define the industrial blueprint for getting there. For 91ÖÆÆ¬³§, this work is a cornerstone of our growing energy transition portfolio and reflects our commitment to building a cleaner, more sustainable world

The post Velocys appeared first on 91ÖÆÆ¬³§.

]]>
Port Arthur LNG /projects/port-arthur-lng/ Sun, 06 Oct 2024 23:51:25 +0000 /?post_type=project&p=451 91ÖÆÆ¬³§ is constructing a natural gas liquefaction and export terminal, helping meet global demand for U.S. energy and low-carbon alternatives.

The post Port Arthur LNG appeared first on 91ÖÆÆ¬³§.

]]>

Reliable Energy for Global Markets

At 91ÖÆÆ¬³§, we are committed to shaping a better world through energy innovation. Our partnership with Sempra Infrastructure is built on enhancing their North American LNG facilities, enabling us to support global energy diversification and transition goals.

As the main contractor under the EPC agreement with Sempra Infrastructure, 91ÖÆÆ¬³§ is proud to lead the construction of the Port Arthur LNG project, ensuring safe and reliable access to U.S. natural gas for markets worldwide.

Heavy Equipment Operator inspects the Hybrid excavator.

Driving Energy Innovation

Currently under construction, the Port Arthur LNG Phase 1 project is a natural gas liquefaction and export terminal in Southeast Texas with direct access to the Gulf of Mexico. The project will include two natural gas liquefaction trains with a production capacity of approximately 13.5 million tonnes per year — sufficient to power around 27,000 households annually, based on average U.S. energy consumption—alongside new natural gas pipelines designed to deliver fuel to the terminal under optimal conditions.

Strengthening Our Workforce with Local Talent

Since receiving Final Notice to Proceed in March 2023, the team has achieved significant milestones, including the cut-and-fill of over 4 million cubic yards of material, the installation of more than 10,000 piles and 18,000 cubic yards of concrete, and the initial installation of structural steel and piping for Train 1. The project’s success is closely tied to the local community, with a reported local hire rate of 51.16% in 2023 and strong partnerships with local vendors.

Project staff pose in front of the Hybrid excavator.

Driving Energy Innovation and Community Growth

27K
Powered

13.5 mtpa is sufficient to power ~ 27,000 households annually

5K
Jobs on Site

At peak, the project is expected to employ approx. 5,000 workers

51.16%
Local Hire

In 2023, the project reported a local hire rate of 51.16%

Supporting the Future Workforce 

Project staff pose in front of excavators at the project site.

Workforce Readiness and Development Initiative

As part of our longstanding partnership with Lamar State College in Port Arthur, Texas, 91ÖÆÆ¬³§ launched a women’s-only Commercial Driver’s License (CDL) training program to both increase opportunities for women and address the shortage of qualified CDL drivers.

Project staff member stands next to the bucket of the Hybrid excavator.

91ÖÆÆ¬³§ Apprenticeship Program 

Partnering with local entities and the Department of Labor in Texas and Louisiana, 91ÖÆÆ¬³§â€™s Apprenticeship Program helps to reskill local residents. We train apprentices using the National Center for Construction Education and Research (NCCER) curriculum and offer them entry-level craft positions upon completion. 

Heavy Equipment Operator and Area ES&H Supervisor atop the Hybrid excavator.

Career and Technical Education Programs 

91ÖÆÆ¬³§ donates thousands of tools to support local high school students enrolled in career and technical education and welding programs, preparing them for sustainable, rewarding, and quality jobs that don’t require college degrees.

Work with Us

To support a diverse and inclusive workforce and supply chain, Port Arthur LNG has several opportunities available to the local workforce and wider community. The workforce is anticipated to reach approximately 5,000 at peak construction.

Explore our available job openings below and start building your next opportunity today!

Register to Be a Supplier

Port Arthur LNG values local suppliers and recognizes the critical role they play in supporting project operations, people, and local communities.

If you supply materials or provide services that Port Arthur LNG is likely to purchase, please register in our Local Supplier Registration portal.

Project staff in discussion at the project site

The post Port Arthur LNG appeared first on 91ÖÆÆ¬³§.

]]>
Pluto Train 2 /projects/pluto-train-2/ Wed, 20 Nov 2024 21:28:09 +0000 /?post_type=project&p=4477 91ÖÆÆ¬³§ is adding a new LNG train and domestic gas facilities at Woodside Energy’s Pluto facility, driving economic benefits for Western Australia.

The post Pluto Train 2 appeared first on 91ÖÆÆ¬³§.

]]>
An aerial view of the Pluto Train 2 jobsite with the ocean on the horizon.

Delivering Economic Benefits for Western Australia Communities

Pluto Train 2 is the expansion of a second LNG train at the existing Pluto LNG onshore facility near Karratha in Western Australia run by Woodside. Pluto Train 2 will process Scarborough gas and have an LNG capacity of ~5 million tonnes per annum. As part of the construction of Pluto Train 2, additional domestic gas infrastructure will be installed to increase capacity to ~ 225 Terajoules per day.

Woodside has selected 91ÖÆÆ¬³§ to deliver the Engineering, Procurement, Construction and Commissioning scope of work for Pluto Train 2.

Woodside is Australia’s leading natural gas producer, and 91ÖÆÆ¬³§ is excited to be working with this key customer to help meet the increasing global demand for LNG as a transitional energy source.

About Pluto Train 2

On 1 January 2022, Woodside Energy issued Full Notice to Proceed (FNTP) to 91ÖÆÆ¬³§ for the Pluto Train 2 Project Engineering, Procurement, and Construction (EPC) scope of work.

The EPC scope of work for 91ÖÆÆ¬³§ includes the construction and commissioning of the second LNG train, domestic gas facilities as well as common utilities, and general facilities at the Pluto LNG Park, and a Construction Accommodation Village located in Gap Ridge.

Woodside Energy

Woodside Energy and 91ÖÆÆ¬³§ are working to maximise opportunities for local, regional and WA businesses and people across the supply chain and through employment, including Indigenous participation opportunities.

Employment

The Pluto Train 2 project is currently recruiting for a variety of construction craft professional roles and professional staff roles.

  • Craft professionals (field based) can apply through our online
  • Professional staff (office based) can apply through the online

Supplier Information

We have continued to maintain strong connections with the Pilbara and Western Australian supply networks, particularly through ICNWA.

If you have not registered with us, send us an email and you will be sent instructions for how to connect. Any packages over $1m will be advertised as they arise on the . 

Woodside Energy and 91ÖÆÆ¬³§ are committed to providing full, fair, and reasonable opportunities for local Australian businesses. We follow the Australian Industry Participation Plan (AIPP) to maximise local industry participation.

The post Pluto Train 2 appeared first on 91ÖÆÆ¬³§.

]]>
Rio Grande LNG /projects/rio-grande-lng/ Wed, 20 Nov 2024 17:11:59 +0000 /?post_type=project&p=4418 Rio Grande LNG is the largest privately funded LNG project in Texas and will add 17.6 million metric tons per year to global LNG capacity.

The post Rio Grande LNG appeared first on 91ÖÆÆ¬³§.

]]>

Meeting Global Demand for Energy

NextDecade is an energy company accelerating the path to a net-zero future.

91ÖÆÆ¬³§ is partnering with NextDecade to support their mission and ensure greater energy security with their Rio Grande LNG (RGLNG) project in Brownsville, Texas. On July 12, 2023, RGLNG issued the notice to proceed (NTP) to 91ÖÆÆ¬³§ Energy Inc. (91ÖÆÆ¬³§) to begin construction of Phase 1 under its lump-sum turnkey engineering, procurement, and construction contracts (EPC).

About the Project

RGLNG is a natural gas and export terminal situated on a 984-acre site on the banks of the Brownsville ship channel. The first phase of the RGLNG project consists of three liquefaction trains, two storage tanks and one marine berth. At full capacity, the five-train facility will have a production capacity of 27 million tonnes per annum (MTPA).

Work with Us

With a great project comes great growth for the local community. During the life of the project, RGLNG will have many opportunities available to the Rio Grande Valley workforce and wider community. The workforce is anticipated to reach approximately 5,000 at peak construction.

Explore our available job openings below and discover your next opportunity today!

  • RGLNG professional staff
  • RGLNG craft professionals
  • RGLNG NextDecade

Register to be a Supplier

RGLNG values local suppliers and recognizes the critical role they play in supporting project operations, people, and local communities.

If you supply materials or provide services that RGLNG is likely to purchase, please register on our Local Supplier Registration portal.

The post Rio Grande LNG appeared first on 91ÖÆÆ¬³§.

]]>
Corpus Christi Liquefaction Project /projects/corpus-christi-liquefaction-project/ Tue, 19 Nov 2024 15:39:32 +0000 /?post_type=project&p=3839 In partnership with Cheniere Energy, 91ÖÆÆ¬³§ is expanding the Corpus Christi Liquefaction project to deliver cleaner, flexible energy worldwide.

The post Corpus Christi Liquefaction Project appeared first on 91ÖÆÆ¬³§.

]]>
Exterior view of LNG tang against a blue sky.
An aerial view ship docked at project site.

Providing Cleaner, More Flexible Energy

selected 91ÖÆÆ¬³§ as their partner to support their efforts to increase global access to liquefied natural gas (LNG) and help meet the growing demand for this cleaner, more reliable, and flexible energy source. 

91ÖÆÆ¬³§ helped Cheniere develop the U.S.’s first greenfield LNG export facility in fifty years, the . LNG is safely and securely sent overseas from the facility’s location on the Texas Gulf Coast. This location is situated near some of the most prolific natural gas producing regions in the country and connected to the U.S. natural gas pipeline network.  

Beyond this project, Cheniere and 91ÖÆÆ¬³§â€¯have worked together for almost two decades. To date, we have completed nine LNG trains between Cheniere’s two Gulf Coast facilities. All nine trains were completed ahead of schedule and within project budgets. With the Stage 3 expansion underway, up to seven additional LNG trains are in the EPC phase to support the growing demand for natural gas around the world. The first train of Stage 3 reached substantial completion in March 2025. 

About the Project

The first two LNG trains were completed in 2019 and the third was completed in 2021. The development of Train 1 won the .

This 1,000+ acre facility contains four liquefaction units, or trains, with a total capacity of roughly 16.5 million tonnes per annum (mtpa).

In March 2025, Cheniere issued 91ÖÆÆ¬³§ a second limited notice to proceed to continue advancing the expansion of CCL Stage 3, known as the Midscale Trains 8-9 and End Flash Gas Project. The expansion will add two midscale trains, powered by Chart Technology, with motor-driven refrigeration compressors, and operational optimizations, such as additional boil-off-gas compression and an end-flash gas unit. When operational, this addition will add 3 mtpa of LNG. 

Operating Facility at a Glance

15M
Tonnes

Total capacity per annum across three trains.

266K
Cubic Meters

Two berths that can receive the world’s largest LNG carrier, the Q-Max, to better meet demand.

480K
Cubic Meters

Three storage tanks holding up to 48,000 cubic meters of LNG.

Uses ConocoPhillips  process to efficiently and effectively cool the natural gas.

Environmental Focus

During the build, the 91ÖÆÆ¬³§ and Cheniere teams facilitated the construction of more than $8 million of breakwater projects to minimize shoreline erosion along the gulf and to protect and enhance sensitive wetland resources.

Equity on Site

The 91ÖÆÆ¬³§ and Cheniere teams partnered with the  to ensure equity by identifying and eliminating barriers among its non-native English speakers. 

91ÖÆÆ¬³§ also partnered with NHEO to create the Building a Safer Future campaign designed for craft professionals to help reduce and ultimately eliminate construction-related hazards.

Onsite Tech Increases Safety and Enhances Communications

The 91ÖÆÆ¬³§ team used 20 innovative solutions to improve cost and schedule. These included drones to survey the site and locate equipment, robotic automation bots to increase efficiency, single interface apps for planning, assigning, tracking, and claiming work packages across a range of field disciplines, and radio frequency identification (RFID) tags for on-time material deliveries.

To keep safe during the pandemic, colleagues also used a mobile app that enabled real-time collaboration with technicians and engineers in the field and those working remote.

Supporting the Local Community

At the onset of the pandemic, the Corpus Christi project team donated more than 30,000 lbs. of food and water to the Coastal Bend Food Bank, gave $16,000 to local charities using profits from an onsite metal recycling program, and donated 1,000 N-95 respirators to the local Fire Department and first responders.

Both  and 91ÖÆÆ¬³§, through its 91ÖÆÆ¬³§ Group foundation, separately donated to the American Red Cross to help after Hurricane Harvey, which significantly impacted the local community in 2017.  

In April 2025, the Corpus Christi Liquefaction Stage 3 (CCL3) project site and Cheniere partnered to enhance Our Children’s Park in Gregory, TX, strengthening our commitments to community support. Volunteers refurbished the basketball court and soccer field goals, resurfaced the splash pad, painted park benches and the sign, mulched play areas, and cleaned up the debris around the park. 

The post Corpus Christi Liquefaction Project appeared first on 91ÖÆÆ¬³§.

]]>
Sabine Pass Liquefaction Project /projects/sabine-pass-liquefaction-project/ Fri, 04 Oct 2024 19:25:27 +0000 /?post_type=project&p=351 Together with Cheniere, 91ÖÆÆ¬³§ built and expanded Cheniere’s Sabine Pass LNG receiving terminal between 2005 and 2009 and added liquefaction capability in 2016.

The post Sabine Pass Liquefaction Project appeared first on 91ÖÆÆ¬³§.

]]>

Quick Turnaround for an LNG Customer

When Cheniere Energy planned its original regasification plant on the Gulf of Mexico, the United States was one of the world’s largest importers of natural gas. Booming gas output from the country’s shale formations subsequently turned that market around.

Together with Cheniere, 91ÖÆÆ¬³§ built and expanded Cheniere’s Sabine Pass LNG receiving terminal between 2005 and 2009 and added liquefaction capability in 2016 so that the terminal’s existing storage tanks, berths, and pipelines could be used for LNG exports.

In September 2022, Sabine Pass Liquefaction (SPL) became the first terminal in the world able to accommodate three LNG tankers simultaneously.

About the Project

The first two LNG trains were completed in 2016. Trains 3 and 4 were completed in 2017 and Train 5 in 2019. The sixth train and third berth at SPL were completed in 2022 ahead of schedule and within budget.

30M
Tonnes

Six trains with total capacity of ~30 million tonnes per annum

1000+
Acres

The 1,000+ acre facility contains six liquefaction trains

3.4B
Cubic Feet

Five storage tanks each capable of holding 3.4 billion cubic feet of LNG

LNG ship at the Sabine Pass dock.

From Shore to Ship

After building Cheniere’s receiving terminal on the shores of the Sabine River estuary, 91ÖÆÆ¬³§ constructed the facility’s six production trains. This conversion to a bidirectional facility allows our customer to liquefy and export U.S natural gas or regasify foreign-sourced LNG, depending on market conditions.

No Rain Checks, No Excuses, No Delays

The completion of Phase 1 of the Sabine Pass LNG terminal was an extraordinary accomplishment.

Shortly after work began in 2005, Hurricane Katrina nearly destroyed nearby New Orleans and contributed to a severe shortage of craft labor throughout the U.S. Gulf Coast. The project later took direct hits from five more tropical storms or hurricanes, including Hurricane Rita, which further devastated the area but did not affect the facility.

Cheniere, 91ÖÆÆ¬³§, and their suppliers worked around the weather events and kept the job on its original schedule. That success earned us a contract in 2006 to expand on our original work. In September 2008, foul weather, that time Hurricane Ike, hit Phase 2. While the installed facilities were mostly untouched, our team’s decisive action minimized damage to materials awaiting installation and kept the work on track.

Training for the (Re)Building Trades

Following Hurricanes Katrina and Rita in 2005, 91ÖÆÆ¬³§ and other Business Roundtable member companies formed the Gulf Coast Workforce Development Initiative as a public-private partnership to help meet demand for skilled construction workers.

Owners, contractors, labor organizations, community colleges, and government agencies recruited and equipped nearly 20,000 workers with construction trade and basic safety skills. The training helped local people rebuild the region and embark on lasting careers.

Partners in Progress

Cheniere and 91ÖÆÆ¬³§ have worked together for more than 15 years. To date, we have completed nine LNG trains between Cheniere’s two Gulf Coast facilities. All nine trains were completed ahead of schedule and within project budgets.

View of new liquefaction project across the river from the Texas side.

The post Sabine Pass Liquefaction Project appeared first on 91ÖÆÆ¬³§.

]]>
Third Generation Project /projects/third-generation-project/ Tue, 19 Nov 2024 22:19:55 +0000 /?post_type=project&p=4265 Led by 91ÖÆÆ¬³§ & ENKA, the Third Generation Project expands Kazakhstan’s oilfield operations with cutting-edge engineering and local workforce leadership.

The post Third Generation Project appeared first on 91ÖÆÆ¬³§.

]]>
Knockout drum at the 3GP jobsite.
A worker at the 3GP jobsite.
Exterior view of job site facility.

Promoting Long-Term Economic Development in Kazakhstan

91ÖÆÆ¬³§ and ENKA, through their joint venture company Senimdi Kurylys (SK), was awarded the Third Generation Project (3GP-West) package at the  in May 2018. Construction of the mechanical, electrical and instrumentation works, pipe fabrication and module stacking, installation and hook-up are included within the scope of the project.

In addition to the 3GP scope, SK continues to support facility upgrades including increasing crude shipment capacity, diesel and fuel storage expansion, flare header upgrade and pipeline repairs.

Workforce Development

Over the past three years working on the 3GP-West package, SK has employed more than 15,800 Kazakhstani nationals, making up more than 80% of the total workforce. Kazakhstani nationals have occupied 60% of the supervisor and higher positions on the project.

SK’s work continues to support economic growth across the country by creating jobs, upskilling the local construction and supervision workforce and providing opportunities for local companies through the supply chain.

The overall success of the program relies heavily on the skills of generations of Kazakhstanis to deliver the facilities needed as part of the expansion project, both through direct employment to build the facility and through local subcontractors and suppliers.

To ensure the workforce has the required skills and to reinforce our safety culture, a Craft Skills Center and a Safety Hazard School were developed to provide practical training across key disciplines needed to safely perform the scope of work on the project.

Training by the Numbers

100K
Hours of Skilled Training

More than 100,000 hours of skills training has been completed by the craft professionals on the project 

19K
Hours of Assessments

More than 19,000 hours of capability assessment have been performed to ensure the effectiveness of the training programs

Areas covered in the craft training program included:

  • Pipefitting
  • Welding
  • Insulating
  • Driver operator
  • Steel erection
  • Flange management
  • Scaffolding
  • Rigging and lifting

Building Local Pipe Fabrication Capability

SK performs pipe fabrication through its on-site facility to support the 3GP scope, including heavy wall spools, clad pipe fabrication, structural steel fabrication and plasma cutting. The facility also includes precast concrete and insulation workshops.

The facility is one of the largest in western Kazakhstan, and works in collaboration with other local facilities which has enabled a growth in local capability to perform pipe galvanizing and clamp bending.

Workers at the 3GP jobsite.

Long Term Partnership

91ÖÆÆ¬³§â€™s relationship within Kazakhstan began in 1993 when we secured our first contract on the Tengiz oil field in a joint venture arrangement with ENKA.

We have had a continual presence on the project for almost 30 years to support the ongoing development, upgrade and operational efficiency of the oil field. This has included debottlenecking projects to increase oil production, Sour Gas Injection project, the Second Generation Plant Project, which was completed in 2008, and ongoing capacity and reliability upgrades to the facility through to the current work on the Third Generation Project (3GP) to further expand the facility.

In Kazakhstan, as in other countries worldwide, we will continue collaborating with communities and customers to build a stable, sustainable, and prosperous future in the regions where we work.

A crane lifting materials at the 3GP jobsite. crane, jobsite

About Senimdi Kurylys (SK)

SK’s primary mission is to be recognized as the construction and engineering contractor of choice by all customers in Kazakhstan. The company’s areas of expertise include civil, structural, mechanical & piping, electrical and instrumentation, insulation, HVAC, and turnarounds.

SK was established by 91ÖÆÆ¬³§ and ENKA in November 2000, as a 100% Kazakh-based company.

The post Third Generation Project appeared first on 91ÖÆÆ¬³§.

]]>
Pennsylvania Chemicals /projects/penn-chem-shell-polymers/ Sun, 06 Oct 2024 23:51:38 +0000 /?post_type=project&p=452 91ÖÆÆ¬³§ built the Shell Polymers Monaca plant, one of the largest manufacturing projects in the U.S., with 9,000 workers at peak construction.

The post Pennsylvania Chemicals appeared first on 91ÖÆÆ¬³§.

]]>
Sunrise behind construction equipment
Supervision of a barge lift-off of material at lift-on lift-off (LOLO).
A worker at the Pennsylvania Chemicals jobsite.

North America’s Largest Construction Site

In 2022, our team completed construction of one of the biggest manufacturing projects in the U.S., the Shell Polymers Monaca plant. At the time, this project marked one of the largest union construction jobs in the U.S. with more than 9,000 workers on site at peak construction. The plant is producing 1.6 million tonnes of polyethylene per year for use in a wide range of everyday products from packaging and containers to automotive components.

The project was nearly a decade in the making, involving craft professionals from across the U.S., represented by 15 unions, working 47 million hours during the construction phase.

Nighttime view of the Pennsylvania Chemicals Site
Professional artistic photo of the Pennsylvania Chemicals site at the height of construction.
Early evening photo of the Pennsylvania Chemicals Plant.

Construction in Numbers 

253
Modules

253 modules produced across four module yards


1620
Pieces

1,620 pieces of equipment


241K
Cubic Yards

The construction phase used 241,000 cubic yards of concrete, 42,000 tons of steel, and over 1 million feet of pipe, highlighting the project’s scale and complexity.


1.6M
Tonnes

The facility can produce 1.6 million tonnes of polyethylene pellets annually, providing essential materials for everyday products.


9K
Jobs

During peak construction, about 9,000 workers contributed to 47 million hours of work across 15 unions.

Workers look out at the Pennsylvania Chemicals site.

Community: A Landmark Megaproject

This megaproject generated significant local economic activity by purchasing materials, equipment, and supplies.

91ÖÆÆ¬³§ prioritized local businesses, collaborating with over 150 local suppliers, including 65 minority- or women-owned companies. The project involved close teamwork among Shell, 91ÖÆÆ¬³§, Great Arrow Builders, unions, and local contractors.

Professional artistic night photo of the Pennsylvania Chemicals site including ethane cracker unit (ECU) furnaces and quench tower.

Located in Potter Township, Beaver County

The facility includes an ethane cracker, three polyethylene units, a 275MW power plant, a water treatment facility, and extensive storage with rail and truck loading capabilities. 91ÖÆÆ¬³§ served as the Main Works Contractor for the entire construction, commissioning, and startup process.

At a Glance

Ethane Cracker Unit
The Quench Tower stands 288 feet tall, equivalent to a 27-story building.

Cogen and Power Supply
Generating approximately 20 megawatts of electricity, the Cogen system powers the entire facility and can supply excess energy to about 2,000 homes in Beaver County.

Polyethylene Production
The plant produces polyethylene (PE) pellets, which are essential for everyday items like food packaging, household products, and toys.

Cooling System
The cooling tower operates with pumps that circulate up to 370,000 gallons of water per minute, maintaining a continuous flow of 2.7 million gallons.

Railyard Infrastructure
The railyard can accommodate 1,400 rail cars along its extensive 30-mile track network.

The post Pennsylvania Chemicals appeared first on 91ÖÆÆ¬³§.

]]>